Panels are lifted using suitable loader or crane and approved lifting gear located in lifting holes of loops cast in panels. This is done after proper study of the lifting capacity of machine, lifters, chains or slings against weights of panels before handling and ensure lifters and chains are fully secured. Position reinforcing bars in holes as drawing before panels are lowered into position. Followed by ensuring correct arrangement of reinforcing bars.

The lifting and installation is carried out after thorough preparation and following all safety standards.